Another month has passed so it is time for another video update on the progress of the PGZ Stocznia Wojenna investment. Installation and finishing works are still underway in both halls. In the Hull Hall, where the Miecznik frigates will be built, we are finishing pouring the floor (permissible load 20 t/m2). All three cranes are already in place. The extensive ventilation system for the halls is also nearing completion.